Leightons Bruce Highway Upgrade

Bruce Highway, QLD
Client TMR
Location Australia, QLD
Schedule 2006 - 2007
Architect Adrian Carroll

Project Detail

BOUNDARY ROAD TO UHLMANN ROAD

This project involved the upgrade and modification of 5 on-ramps southbound on the Bruce Highway, as part of the ongoing solution to the traffic issues surrounding this notorious section of road. The upgrade would increase the current capacity of the highway, and allow the traffic to flow more freely during peak hours and reduce the heavy congestion.

The scope of works included the complex traffic management involving lane closures and night works, complex project management requirements to support works which included, civil earthworks, drainage, pavement reconstruction, street lighting and electrical communications, installation of road furniture including guardrail.